Does the Security of Payment Act Apply to Your Project?
Does the Security of Payment Act Apply to Your Project?
This is general information, not legal advice. The Building and Construction Industry Security of Payment Act 2009 (SA) is a strict, deadline-driven statute, and a live payment claim or dispute under it should go to a solicitor before you respond, not be decided from an article. Figures current as at 7 November 2026 — check the current authorised version of the Act at legislation.sa.gov.au before acting, since legislation can change.
Short answer: if you're an owner developing land you don't live in — townhouses for sale, a multi-dwelling project, a rebuild you won't occupy — the Act almost certainly applies to your building contract, even though it's commonly discussed as protection "for the builder." That matters because, in that relationship, you are usually the one on the receiving end of its payment claims, not the one shielded by its exclusion.
The exclusion catches owner-occupiers, not developers
Section 7(2)(b) of the Act carves out "a construction contract for the carrying out of domestic building work … on such part of any premises that the party for whom the work is carried out resides in or proposes to reside in." That's the only residential exclusion in the Act, and it turns entirely on occupancy, not on how big or small the project is. A single owner-builder extending the house they live in sits outside the Act. An owner building six townhouses to sell, or a dual-occupancy they intend to rent out, does not reside or propose to reside in the premises — so the exclusion doesn't apply, and the Act governs the construction contract.
This is the assumption worth checking first, because "SA has protections for builders getting paid" is often heard as "this doesn't involve me as the owner." It does. The Act's object (section 3) is to grant a statutory entitlement to progress payments to whoever carries out construction work under a contract — your builder, and your builder's subcontractors and consultants in turn — regardless of what your contract says. Section 33 makes that override non-negotiable: a contract clause purporting to exclude or restrict the Act is void.
Who the machinery actually runs against
Once the exclusion doesn't apply, you are typically the "respondent" under the Act — the party a payment claim is served on — in your contract with your builder. That position comes with a timetable, not a negotiation:
Your builder (or any subcontractor claiming through the chain) can serve a payment claim at any point from the relevant reference date, within the contract's own claim window or 6 months after the work was last carried out, whichever is later (s13).
You then have 15 business days (or your contract's shorter stated period) to reply with a payment schedule stating what you'll pay and, if less than claimed, why (s14).
If you say nothing within that window, you become liable for the full claimed amount by default — and if the claimant sues to recover it as a debt, you're not entitled to raise a cross-claim or a defence about the underlying work (s15).
Even if you do respond but don't pay the scheduled amount, or the claimant disputes your scheduled figure, the claimant can take the dispute to adjudication — a statutory decision-maker who must determine the matter within 10 business days of receiving submissions, considering only the contract, the claim, the schedule and any site inspection (ss17, 21, 22).
An adjudicator's determination can be filed as a court judgment and enforced — again, without you being able to bring a cross-claim or re-argue the contract in proceedings to set it aside (s25).
None of this replaces your other contractual rights over defects, delay or quality — section 3(4) says the Act doesn't limit any other entitlement or remedy you have. But it does mean the payment dispute runs on its own fast, largely procedural track, separate from — and usually faster than — however you'd otherwise resolve a contract disagreement.
A hypothetical, to make the stakes concrete
Say a developer building four townhouses for sale gets a payment claim from the builder for a progress stage the developer believes is incomplete. If the developer simply ignores it, intending to deal with it "once the stage is actually finished," the 15-business-day payment-schedule window can run out before that conversation happens — at which point the developer owes the full claimed amount and has given up the right to dispute it through the ordinary debt-recovery process. The lawful response isn't to pay regardless; it's to serve a payment schedule within the window, in writing, stating the amount you propose to pay and your reasons for withholding the rest (s14(2)–(3)) — which preserves your position whether the dispute then settles or goes to adjudication.
What to check in your contract and structure now
Confirm, in writing with your own solicitor, whether any part of your current build is one you or a related party resides in or proposes to reside in — that single fact decides whether the Act applies at all.
Check who in your project team is responsible for recognising an incoming document as a "payment claim made under this Act" and calendaring the response deadline — a claim doesn't have to look formal to count, if it meets section 13's requirements.
Review how your building contract defines reference dates and claim timing, since the Act's defaults only fill gaps your contract leaves open (ss4, 11).
If you're comparing builder quotes or structuring payment stages, line up how provisional sums and milestone payments interact with this claim cycle — see our guide to reading builder quotes side by side and to fixed-price versus cost-plus contracts.
If a payment dispute escalates toward a builder's financial distress rather than a straightforward claim, the order of events differs again — see what an owner still holds after the builder is appointed and what happens when a builder enters liquidation mid-build.
It's also worth noting that a 2021 bill proposing to extend the Act's coverage into some residential contracts was introduced in SA Parliament but was not passed — the Act's domestic-occupancy exclusion in section 7(2)(b) remains as described above as at this article's date. Confirm the current position before relying on it, since legislation can change.
What to do this week
Get written confirmation from your solicitor on whether your project is covered by the Act or falls under the owner-occupier exclusion.
Identify who on your side is responsible for spotting a payment claim and calendaring the 15-business-day (or contract-stated) response deadline.
If you've received a claim you dispute, don't go silent — get a compliant payment schedule served within the window, with your solicitor's input on the reasons for withholding any amount.
Cross-check your contract's payment and reference-date clauses against the Act's defaults, so you know which rules actually govern your project.
A payment claim under this Act runs on a short, strict clock, and the cost of missing it isn't a weaker negotiating position — it's a statutory debt you can't contest. If you want help getting your project's contracts and payment processes reviewed before a dispute arises, talk to a development manager.
About the author
Lin Yuan
Expert property development and project management insights.